Allow switching the time format to 100 minute fractional format
It would be really nice to be able to switch the time format used to the fractional (industrial?) format where one hour is divided into 100 units. E.g., 6:45 would become 6.75.
-
Lukasz commented
This is common in other PM managers like MS Project where any duration can be displayed in any unit, much like how Excel actually stores dates and time as decimal and later translates only the display. The catch is, in MS Project, I believe that one can establish a global setting per project that 1 day = 8 hrs, so if someone enters 8h, it could be displayed at 1d rather than 0.33d. Additionally, MS Project handles "1d" by day of week and considers holidays. I think a simple decimal veiw with one global or task group level setting of 'how many hours in a day' would be more than sufficient.